Sprint board Sprint burndown (hours) Sprint burndown (SPs) ヘルプ

Sprint board help

PBIs & tasks

An Sprint board includes PBIs & tasks. PBIs (or Product Backlog Items) are typically user stories, bugs, technical debts... and they are composed of child tasks. Under Administration » Plugins » Scrum Redmine plugin you can configure which issue trackers are considered PBIs and which are considered tasks.

PBIs are located on the left part of the board, tasks on the right columns. There is a column per possible task status (these statuses are configurable under Administration » Plugins » Scrum Redmine plugin).

A lot of the described features are enabled only with permissions, so take a look to Administration » Roles & permissions » Permissions report to enable/disable permissions for each role.

Working with PBIs

PBIs can be created in this board with the links at the end of the board or moved from the product backlog view.

Once you have PBIs on the Sprint board, you can dragged in vertical to change their order (so the team will start with the ones at the beginning). In the PBI post-it you will see its attributes (to enable more/less attributes take a look to Administration » Plugins » Scrum Redmine plugin). You can edit them clicking on the pencil icon.

PBIs are estimated in story points (SPs), you can edit directly this value clicking on the SPs value and typing a new value (then press ENTER or TAB). If use remaining story points is enabled (under Administration » Plugins » Scrum Redmine plugin) then you will see that field also in the post-it, it's also editable; this is used to calculate a precise Sprint burndown by SPs, so don't forget to update it day by day (before leaving the office).

Working with tasks

Tasks are technical things to be done in order to complete a PBI. They can be created directly clicking on the icon in the PBI post-its (or creating new child issues from the PBI issue form).

To change task status, just drag & drop in horizontal direction (or edit & change its status). Take care of your tracker work flow, because maybe some movements are forbidden for some roles (ask your administrators). There are a few automatic actions involved when you move task post-its (take a look to Administration » Plugins » Scrum Redmine plugin to enable/configure them):

  • When you move the first task from new (first tracker state defined in the admin settings) to any other state, the plugin change parent PBI status to in progress (the second state).
  • When you change a task status to anything but new, and it has not assignee, the plugin set it to current user; if the task is changed to new status, the assignee is removed.
  • When the last task is closed, the remaining effort is set to zero and the parent PBI is changed to a configurable status (i.e. resolved).

Tasks are estimated in hours, using the estimated effort field, this is also editable in the post-it. In order to calculate an Sprint burndown by hours is also necessary to fill the remaining effort field (day by day). You can log time to the tasks clicking on log entry icon.

As soon as you assign a task or log time into it, an orange mini-post-it (color is configurable under Administration » Plugins » Scrum Redmine plugin) is attached to the task, and a green one in case you log review time (review time has also to be configured under Administration » Plugins » Scrum Redmine plugin). This allow to follow up how is doing what easily.


Support this Redmine Scrum plugin

In order to be an open source & free plugin, I need your support:

or

Kindly regards,
Emilio González Montaña

Sprint board

2025-06-06

2025-06-22

庭関連

1/5
2.0/9.0
22.2%

Product backlog items たぶんいつかやる たぶん明日やる 今やってる たぶん終わった ほんとに終わった やっぱなし
#485: アプローチ作成
対象フェーズ: 庭関連
Blocked: いいえ
StoryPoint: 2
Simple PBI: いいえ
sp 29h
#487: 砂利設置
masaya_abe
masaya_abe
7h h
#488: 防草シート
masaya_abe
masaya_abe
5h h
#489: 木材の埋設
masaya_abe
masaya_abe
5h h
#495: 除草剤撒く
masaya_abe
masaya_abe
5h h
#486: 花壇の設置
対象フェーズ: 庭関連
Blocked: いいえ
StoryPoint: 2
Simple PBI: いいえ
sp 23h
#496: ユーカリ植え付け
masaya_abe
h
#490: 畔板の設置
masaya_abe
masaya_abe
7h h
#491: 木材の埋設
masaya_abe
masaya_abe
5h h
#492: 用土の布設
masaya_abe
masaya_abe
4h h
#493: 花壇のレイアウト
masaya_abe
masaya_abe
5h h
#494: 花壇の植え付け
masaya_abe
masaya_abe
2h h
#497: アスチベル植え付け
masaya_abe
masaya_abe
2h h
#498: アジサイ植え付け
masaya_abe
masaya_abe
2h h
#499: 縁側前砂利
対象フェーズ: 庭関連
Blocked: いいえ
StoryPoint: 1
Simple PBI: いいえ
sp
#500: 砂利調達
masaya_abe
h
#501: 掃除
masaya_abe
h
#502: 防草シート布設
masaya_abe
h
#503: 砂利設置
masaya_abe
h
#504: 下草植え付け,草刈りなど仕上げ
対象フェーズ: トイレリフォーム
Blocked: いいえ
StoryPoint: 2
Simple PBI: いいえ
sp
#510: 下草調達
masaya_abe
masaya_abe
1h h
#511: 適当に植え付け
masaya_abe
masaya_abe
2h h
#505: 旧池
対象フェーズ: トイレリフォーム
Blocked: いいえ
StoryPoint: 2
Simple PBI: いいえ
sp
#506: 砂の撤去
masaya_abe
h
#507: 配水の整備
masaya_abe
h
#508: 土入れ
masaya_abe
h
#509: 何植えるか
masaya_abe
h